DIFFERENT CITIES - DIFFERENT RULES
DOI:
https://doi.org/10.52340/building.2024.01.69.19Keywords:
construction permits, Batumi, Tbilisi, procedure, law, standards, spatial planning, rulesAbstract
The article presents the differences in construction norms and the accompanying processes on the example of two cities in Georgia: Tbilisi and Batumi.
The main research question is to make a general analysis and outline a unified picture of how permits are obtained in different cities of Georgia, when the country’s two main cities are taken for comparison, where the construction processes are taking place most intensively and the changes in the legal norms lead to many bureaucratic differences and shifting of the construction area.
The general permit conditions and rules applicable in the country are similar, the basic structure of these processes is the same, although there are issues that are tested differently in different administrative units.
In order to better illustrate the differences, the study provides several tables, and mostly they include process comparisons.
The main differences are found in development rules and there are differences in permitting processes as well.
Downloads
References
Resolution #255 on the procedure and conditions for issuing a construction permit and putting the building into operation (In Georgian).
Government Decree #261 on the basic provisions for the regulation of the use and development of territories (In Georgian).
Code of Spatial Planning, Architectural and Construction Activities of Georgia (In Georgian).
Resolution of the City Council #14-39 St. On the approval of the rules for regulating the use and development of territories of Tbilisi Municipality (In Georgian).
Resolution #59 of the government on the approval of the technical regulation - the basic provisions of the regulation of the use and development of the territories of the settlements. (In Georgian).
Decree of the Government #57 on the rules and conditions of the construction permit (In Georgian)